Go to JB Company Parameters and check the box to "Allow Changes to Previous and Contract Amounts". Contract Units, Contract Amount, Previous Units, and Previous Amount fields are available for input and previous and contract amounts may be changed for existing and/or new invoices. Changes to 'previous' amounts only affect the figures that print on invoices. Changes do not update General Ledger, Accounts Receivable, or Job Cost. Typically, you will only check this option when setting up the Job Billing module.

Only change the previous amounts if this is the last bill on the contract otherwise run the auto update from the first bill on the contract from the file menu.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article