Create a Folder

5-Projections

Put these items in the folder to create a good flow for projections


PMCP1. Go into PM Cost Projects




PMCP2. Enter your Projection Code Date



PMCP3. Project: Press f4 and select the project you want to make projections on.



PMCP4. This window will pop up:

Write Over Plugged Values - Never

Initialized Worksheet Detail Option - None



PMCP5. This window will pop up:



PMCP6. Go into the columns and update your costs 



PMCP7. Submit your projections



PMCP8. Validate and Post Batch